Site attributes

Seventeen attributes, and exactly how far each one is proven

Four asset owners responded to a Before You Dig Australia enquiry on 26 August 2026, followed by a site inspection on 27 August. The results identify a substantial combination of energy, connectivity, land, climate and access advantages, with grid capacity, fibre diversity, water strategy and the energy precinct configuration now forming the four gating questions for feasibility, and planning running alongside. The NSW Guidelines page sets out how the same evidence reads against the seventeen performance measures.

Read the position column literally. “Confirmed” means an asset owner has confirmed the asset exists. It does not mean capacity, approval or service is secured, and nothing on this page should be read that way.

Where the evidence sits

4 Confirmed An asset owner has confirmed the asset exists. Capacity is a separate question.
5 Strong evidence Documented or measured, and consistent across more than one source.
2 Development opportunities Not a constraint. A design or commercial decision still to be made.
6 Verification priorities The open items, including the four gating questions. These govern the next stage of feasibility.

The attributes in full

Search, filter and sort the seventeen attributes. Every filter is reflected in the address bar, so a filtered view can be linked to or emailed.

Showing all 17 attributes.

Site investment attributes, with the evidence position, the investor benefit, the current evidence and the next verification step for each
Attribute Position Investor benefit Evidence and current position Next verification Detail
EnergyHigh-pressure gas Confirmed Potential on-site energy firming and generation pathway. Jemena confirms the site could affect the high-pressure Eastern Gas Pipeline, identified as EGP Midline. Confirm industrial offtake feasibility, capacity, pressure, connection cost and delivery timeframe.
Energy132 kV power Confirmed Direct proximity to high-voltage infrastructure reduces the need for a long connection corridor. Asset plates identify feeder 97R, Cooma to Bega, on double-circuit-capable poles, with the second circuit position vacant. Obtain network-owner confirmation of voltage, configuration and feasible point of connection.
EnergyGrid capacity Verification priority A confirmed staged connection could support development from an initial facility to a larger campus. No firm rating or available capacity has been established for feeder 97R. A 114 MW wind generator already exports through the network. Submit staged 25, 50, 100 and 200 MW load scenarios to the relevant network providers.
ConnectivityCarrier fibre Strong evidence Existing carrier infrastructure may provide a faster and less costly route to high-capacity connectivity. Telstra issued an explicit major-cable and optic-fibre warning. NBN separately identified communications assets. Confirm dark fibre or wavelength availability, capacity, splice points, latency and commercial terms.
ConnectivityDiversity Development opportunity Physically separate fibre paths would support carrier-grade redundancy and operational resilience. One significant communications corridor is strongly indicated, but a diverse second route is not established. Obtain route maps and feasibility responses from Telstra and at least one second carrier.
ConnectivityLatency To be validated Cooma’s position between Canberra, Sydney and Melbourne may suit regional compute and resilience workloads. Geographic positioning is favourable, but carrier performance has not been measured. Obtain indicative and tested latency to Canberra, Sydney and Melbourne network locations.
SiteLand Strong evidence A large, predominantly clear holding supports flexible campus design and infrastructure separation. Up to 837.7 hectares of predominantly open grazing land across 11 lots as supplied. Confirm survey area, developable footprint, slopes, geotechnical conditions and environmental constraints.
SiteScalability Strong evidence The landholding could accommodate staged construction, energy infrastructure, setbacks and future expansion. The property provides substantial land relative to a typical data centre campus. Prepare indicative 50, 100 and 200 MW campus layouts.
SiteSite control To be validated Consolidated ownership or control can reduce acquisition complexity and improve delivery certainty. The proposed site extends across 11 lots as supplied. Complete ownership and title evidence has not been presented here. Verify ownership, title, easements, restrictions and control of every required lot.
SiteHighway access Confirmed Direct highway frontage supports construction logistics, heavy vehicles and ongoing maintenance access. The Monaro Highway B23, classified as State road HW19, runs approximately 3.9 km through the holding. Confirm intersection design, heavy-vehicle access and Transport for NSW requirements.
OperationsClimate Strong evidence Cool conditions and elevation may reduce mechanical cooling demand, energy consumption and operating costs. Cooma has an annual mean maximum temperature of approximately 18.2 to 19.4 °C at about 850 to 900 metres elevation. Undertake hourly-temperature, free-cooling and indicative PUE modelling.
OperationsWater Design opportunity An air-cooled or low-water architecture could reduce dependence on a new large-scale water supply. No large-scale water supply has been demonstrated. The requirement will depend on cooling design. Compare air-cooled, closed-loop and hybrid cooling options and confirm operational demand.
OperationsWorkforce Regional advantage Proximity to Cooma provides access to services, accommodation, emergency response and a regional workforce. The site is close to an established regional centre and directly connected by the Monaro Highway. Assess construction workforce, specialist technical labour, accommodation and training partnerships.
DevelopmentPlanning Verification priority NSW provides established assessment pathways for major data centre developments. The land is understood to be RU1 Primary Production, which is not a prescribed data centre zone. A specific pathway is required. Obtain formal advice on permissibility, rezoning, planning proposal and State Significant Development pathways.
DevelopmentResilience Development opportunity Power, gas, fibre, highway access and a large landholding provide ingredients for a resilient campus. Several infrastructure systems are present or strongly indicated, but the complete redundant design is not established. Prepare an integrated resilience design covering power, fibre, cooling, access and backup systems.
SustainabilityRenewables Strong potential Solar, battery storage and low-energy cooling could support a competitive low-carbon campus proposition. The site has substantial land, cool climatic conditions and access to regional energy infrastructure. Model on-site solar, BESS, renewable power purchasing and grid-support options.
SustainabilityCommunity Development opportunity Regional investment, construction activity and infrastructure improvements could create measurable local benefits. The project is at an early stage and no community-benefit program has been defined. Develop local procurement, skills, environmental and community-engagement commitments.
How to read the positions

Confirmed means the asset owner has confirmed the asset is there. Strong evidence means it is documented or measured and consistent across sources. Development and design opportunity mean a decision is still open, not that something is wrong. Verification priority and to be validated are the genuine unknowns, and the two that govern the project are grid capacity and the planning pathway.

The key facts

What rarely sits on one holding, and what each fact does not yet establish

Land
up to 837.7 haAbout 2,070 acres across 11 lots as supplied. Room to investigate data halls, solar, storage and setbacks; the developable footprint is still to be established. The site →
Scale
50 to 300 MWThe scale of data centre development being investigated, in stages. Not confirmed grid capacity. The opportunity →
Electricity
132 + 66 kVBoth lines cross the holding on Lot 1, and regional wind already exports on the 132 kV. Available capacity is untested. Power →
Gas
Eastern Gas PipelineHigh pressure transmission main crosses Lot 1, confirmed present by Jemena. Pressure, offtake and terms are for Jemena to answer. Energy →
Data and connectivity
Optical fibre at the boundaryTelstra’s own fibre markers on the fence line, and an NBN asset identified. Capacity, diversity and carrier options to establish. Connectivity →
Water
Designed for low waterA cool climate at about 900 m may support closed loop or hybrid cooling. No supply has been demonstrated. Water →
Location
10 km to CoomaA town of about 6,700 people, none of it within 4 km: potential access to workforce and services with separation from residential areas. Canberra 126 km, Sydney 406 km, Melbourne 630 km by road. Distance from Cooma →
Renewables
Wind on the line, solar to investigateBoco Rock wind exports on feeder 97R today. On-site solar and storage are opportunities to investigate; no supply is committed to this site. Energy →

Presence and position only. No electrical capacity, gas capacity, telecommunications service, water supply or planning approval is claimed, secured or offered.

Next step

Move from opportunity to feasibility

Rock Flat is seeking engagement with experienced digital infrastructure, energy and investment partners to undertake the next stage of technical and commercial feasibility. Detailed title, infrastructure, utility and commercial information is available to qualified parties.